MIDDLETOWN PUBLIC SCHOOLS
Furniture and Equipment Policy
POLICY DEFINED
– The Department
of Facilities Management for the Middletown Public Schools is accountable for
ensuring that any acquisition, alteration or donation of furniture and
equipment comply with code requirements, conform to
a.
OSHA Standards, Accessibility Standards and Furniture Fire Rating
Standards will used for planning purposes.
b.
Deviations from approved standards may only be made with the written
approval of the Director of Facilities Management, the Building Department
and/or Fire Department depending on the deviation requested.
2.
Once the faculty/staff receives approval for the furniture/equipment
plan, the person requesting the item(s) will obtain price quotations from the
furniture vendor. If the furniture/equipment is not a
3.
The Director of Facilities Management or a designee will determine the
power, lighting, voice/data, and other needs to support the furniture or
equipment layout.
4.
The Director of Facilities Management or a designee for review and
approval by the Superintendent of School or her designee will prepare a final
budget for furniture, equipment, and infrastructure changes.
5.
When the final budget is approved and the source of funding secured two
things will occur:
a.
The Business Office will place an order with the vendor, and
b.
The Department of Facilities Management will make, or have made, the
necessary infrastructure improvements.
6.
When the furniture or equipment shipment arrives, the Department of
Facilities Management- Shipping and Receiving Clerk will have responsibility
for receiving and entering information into SchoolDude for preventive
maintenance and/or on a Project Spread Sheet. All equipment worth $5000 or more
will be considered a capital asset. These items must be marked and placed on
the capital asset equipment list for yearly inventory.
7.
The Department of Facilities Management will have responsibility for
overseeing the installation of the product and its connection to the Schools
infrastructure.
8.
A Punch List inspection will be conducted by the Department of
Facilities Management with the faculty/staff to ensure that all components have
been installed and are in proper working order.
9.
Following completion of the Punch List, the faculty/staff will be required
to sign-off on the project. This
signature of approval will mark the end of the work.