From
the Desk of
Director
of Facility Management
I. DISTRICT
A.
Facilities Department
Reorganization: Update
1.
A facility team meeting took place on January 25,
2005 to discuss the reorganization, the supervisor’s job description and the
rotating weekend schedule that the Maintenance, Grounds and Project Teams will
be adopting.
2.
3.
The new rotating schedule went into effect on
B.
Architect Study for
1.
Bonne De Sousa and
2.
The full written report will include: a) floor plans
of the buildings; b) “As is” report on updates needed and code issues.
C.
OSHA visit:
1.
This is an annual visit. A report is forthcoming.
D.
1.
Bookshelves: Ongoing
Project
The facilities
department continues to build and install bookcases at the High School and
Gaudet. The elementary schools will be scheduled next.
2.
Sound System: The PTG from
3.
Playground:
E.
IP phone system: Update
1.
2.
Linda
met with Cox to find out about a new phone system, rewiring Aquidneck, and
Voice Mail. We are waiting for the cost of this system. Because of monetary
concerns this may be the stop gap
needed at this time. We won’t know until we get the price.
F.
Door Replacement, Repairs, and Upgrades and Security: Update (CIP)
1.
NE
School Services has been doing the hardware updates (per Fire Marshall’s
request) and repairs over the last couple of weeks.
2.
Mulleng
Systems Management has written an RFP (MHS: exterior cameras, swipe card and
badge system, monitor, door “buzzer” and DVR. JFK/Forest/Gaudet: front door
camera, monitor and buzzer. Aquidneck already has this system.).
3.
G. Paving RFP:
1.
Louis
Berger Group has completed the RFP.
2.
The
school system has applied to the DEM for a Freshwater Wetlands Permit at the
west parking lot of
3.
If
this is permitted, the school system won’t have to cut up the existing asphalt
and create more problems with the existing asphalt.
4.
We
will go out for bid after we get a ruling from DEM
H. Indoor Air Quality: Update
1.
A
summary of the report is enclosed. The complete report (charts and numbers) is
located in
2.
A
copy of this summary report will be on the web and the full report is located
in the Facility Directors office.
I.
Town Hall: Update
Shawn Brown has asked that we put this job on
hold for now.
J.
Various Smaller Projects: Update
1.
The
facilities team is in the process of building wall cabinets for the
school business office. (Complete)
2.
Beth
is working with Sign-a-rama on fire retardant banners for the high
school and middle school indicating their status as Regents Commended. (the
Superintendent and Asst. Superintendent are reviewing the drawings).
II.
A. Painting
Schedule: Continuation
Thanks to the patience
of the Gaudet faculty and Vinnie Giuliano we are proceeding nicely with the
painting of the classrooms. All classrooms on the lower level are complete and
facilities have started on the second level.
B. Data and electrical
for Computers: Bond Update
1.
Coastal Electric has started on the wiring in the remaining
classrooms in the Middle School.
2.
We anticipate that Gaudet will be completely wired in
the next few months.
C.
Greenhouse Gas Reduction Incentive
Program: Complete
School Committee
member, Ned Draper, encouraged us to apply for an energy incentive through the RI State Energy
Office. In November we had to replace a
water heater for the kitchen
at Gaudet. This program allows for a $400 incentive if accepted. I spoke to the
Energy Office on
We do not qualify because applicants must have an average demand
use of 100 kw monthly or
less. Our average demand is 240 kw monthly.
D.
Roof Top Chiller:
At the end of last cooling season we were having some problems will a few
coil leaks in the new chiller. McQuay (subcontractor of Honeywell) had an
engineer evaluate this problem and they think that the best bet would be to
replace the chiller in March rather than fix the coils.
E.
Elusive water leak in Library: (Complete)
Fury Roofers has been call to repair a water leak in the library office
several times. Each time they have been unsuccessful. We removed some of the
ceiling to find that it wasn’t the roof, but a drain pipe that takes a
circuitous route behind a steel I-beam into the middle of the office. This
drain pipe has been tested several times, but it only seemed to leak with after
a huge downpour. The drain has been repaired.
III. HIGH
SCHOOL
A. I.T. Server Room/IT Work Room/IT
Storage: (Temporarily On Hold)
1. The old “
a. Work room and Storage: A workbench for
doing computer repairs and an area for storing parts; equipment, etc. will be
built when soon.
B.
Odor in Administration/Guidance Offices: (Complete)
1.
These
offices have had an odor that seems to come and go for quite a while.
2.
We
had 2 visits from the gas company, 3 from the plumber, emptied the acid
neutralization tank and spoke with a consultant before getting to the bottom of
this mysterious odor.
3.
We
had the same problem as
4.
We
have changed the tiles in the guidance hallway, conference room, and guidance
offices. The odor has been gone for over a week.
C.
Lab tables: (In
process)
The tops of the lab
tables in four of the old science rooms have become loose with age. The
facilities project team is removing each resin top, leveling the cabinets, making
new interior cabinet bottoms, refastening the sinks, and refastening the tops
on these tables. The gas piping has been cut off to these tables and will be
reinstated if the class requires gas. Most do not.
IV.
A.
Exterior Trim LeadLock and Paint: (Ongoing Maintenance
and Lead Encasement)
On hold until spring
V.
A.
Windows: (Bond)
1.
Newport
Glass Co. is in the process of replacing all Plexiglas windows in the front of
JFK and on the North side. This will exhaust the bond funds made available to
the school for window replacement (Oliphant top floor, MHS, Gaudet, front of
JFK)-
a. Installation complete, but we need warmer and
dry weather to do the outside caulking.
2.
We
have ordered new blinds for the windows in front and north side of the
building. (not bond)
VI.
An engineer from Fury
Roofing has been out to look at the pitched roof at the cafeteria side of the “new wing”. Fury has
tried to repair a leak several times without success.
VII.
OLIPHANT
A.
First floor:
In order to comply with fire codes and to make the clerical
offices at Oliphant more efficient, the
facilities team is doing the following:
i. Installed donated
modular furniture in the main clerical office. Complete
ii. Make a work room out of
a former office so that less people walk through causing disruption of work. In process
iii. Will install a small
kitchen with heat detector in the office formally occupied by the Safety
Officer. Most of the equipment needed for this project are already in stock:
small refrigerator, microwave, sink, etc. (In the planning stages)