JANUARY REPORT SUBMITTED BY EDWARD COLLINS
BUILDINGS AND
GROUNDS
DISTRICT WIDE
PROJECT LIST
1) FLOORING: ongoing replacement program
i) JFK- COMPLETE
ii) High School- gym foyer-COMPLETE
iii) High School-asbestos removal top hallway-COMPLETE
Seven classrooms scheduled for February vacation
2) EXTERIOR PAINTING/LEAD ENCAPSULATION
i) High School- 80% done
ii) Gaudet- 80% done
iii) JFK- 25% done
ON HOLD UNTILL SPRING
3) INTERIOR PAINTING
i)
Rest of building-in progress
4) BLINDS
i) JFK-COMPLETE
ii) Gaudet -COMPLETE
\
5) PAVING
i) Gaudet- finish curbing and sidewalks
ii) Aquidneck- front entrance /spring
iii)
ON HOLD FOR SPRING
6) EXTERIOR DOOR ACCESSIBILITY
i) JFK-ramp and railing-COMPLETE
ii) JFK-repair thresholds at all doors-COMPLETE
7) INTERIOR DOOR HARDWARE
i) Gaudet-custodial and office doors-in progress
8) ROOF
i) Aquidneck- in spring
ii) High School-section of roof over 248-COMPLETE
9) FIRE UPGRADE
i) High School- addition of pull station/heat-smoke and strobes 95%
10) GENERATORS
iii) High School- in progress/also new electrical service and removal of old transformer- in progress
iv) Gaudet-in progress
v) Oliphant- in progress
11) FIELDS- slicing/aerating/seeding/fertilize/lime
i) High School- front practice area-COMPOLETE
ii) Gaudet-baseball/football/practice area-COMPLETE
Placed turf blanket on football field
12) FIELDS- re-crowning
iii) High School- practice area’s -COMPLETE
iv) Gaudet- practice area’s-COMPLETE
v) Gaudet- Football field/ Waverly landscaping-COMPLETE
13) FRENCH DRAINAGE SYSTEM
vi) Gaudet- easement on side of cafeteria-COMPLETE
vii) Aquidneck- bottom area along addition-COMPLETE