BUILDINGS AND GROUNDS

 

District Wide Project List 2005-2006

 

1)      Flooring: ongoing replacement program

 

    1. Gaudet - lower one half of lower level - Complete

Rest scheduled for April vacation/CIP money - Complete

    1. Forest Avenue School:  Special Ed Room (102) – Complete

 

2)      Whiteboards:  On-going in-house chalkboard replacement

 

a.           Middletown High School - Complete

b.          Gaudet School - Complete

c.           Elementary – 70% done

 

3)      Bulletin Boards:  On-going in-house replacement program

 

a.           Middletown High School - 80% done

b.          Gaudet School - 80% done

c.           Elementary – 90% done

 

4)      Exterior Painting and Lead Encapsulation:  In-house program

 

a.           Middletown High School - 75% done

b.          Gaudet School - 50% done

c.           Elementary – On hold until Spring

d.          Re-striping of parking lots – 50% done

 

5)       Interior Painting:  On-going in-house program

 

a.             Middletown High School – Painting of gym entrance – Complete

b.            Gaudet School – Complete

c.             J.F. Kennedy School – All but four rooms complete

d.            Aquidneck School – 90% complete

 

6)         Bookcases:   On-going in-house program

 

a.          Middletown High School – 95% done

b.          Gaudet School – 95% done

c.         J.F. Kennedy School – 75% done.  Built new front desk and reception area in library. – Complete

d.        Aquidneck & Forest Avenue Schools - On hold/need funding

 

7)      Paving, Safety and Drainage Program:  10-year management plan written by Louis Berger Group.

 

a.          Gaudet School - Entrance and front parking lot scheduled for spring/ CIP money

b.          Forest Avenue School - Front parking and drive scheduled for spring/CIP money

c.           Forest Avenue School – Front walkway/CIP money - Complete

 

PRESENTLY GETTING QUOTES FOR DIFFERENT AREA’S – Complete.  Will be scheduling work for spring

 

8)      Interior ADA Signage Plan:  Part of 5-year ADA improvement program

 

a.          Middletown High School – Complete

b.          Rest of District – On-going/20% done

 

  9)    Interior Door hardware:  On-going program to make all door hardware ADA     compliant

 

a.             Middletown High School – Complete

 

10)   Acoustics:  The following areas have been designated for some type of acoustical   treatment

 

a.       Forest Avenue School Gym – No Action

b.       J. F. Kennedy School Cafeteria – No Action

c.       J.H. Gaudet School Cafeteria – No Action

 

11)      Roof Update:  Bond/Insurance

 

a.             J.H. Gaudet School - Add four roof drains - Complete

b.            Aquidneck School – Repaired leak in Annex - Complete

c.             Middletown High School - Section of foyer roof entering gym and cafeteria roof was damaged due to storm - Complete

 

12)    Rest rooms:  District-wide ADA upgrades based on 5-year plan

 

a)      Replace Bradley sinks

1)  Gaudet - Complete

2)  High School - Complete

b)      Replace gravity feed urinals - Complete

c)   Increase size of stalls to comply with ADA

1)  MHS - Complete

2)  Gaudet – Complete

d)      Lower mirrors - in progress

1.       Middletown High School - Complete/will add regular mirrors

2.       J.H. Gaudet School - Complete

 

13)   Add grab bars

a)     Middletown High School – Complete

b)      J.H. Gaudet School - Complete

 

14)      Other ADA-

a)      Forest Avenue School - Remove large box covering old toilet area and repair floor - No action

b)      Middletown High School - Remodel nurses room - Complete

 

15)   Other plumbing improvements:

 

a)      Add two sinks in annex at J.F. Kennedy School - Complete

 

16)   Handrails:  District-wide - No action

 

17)   Exterior Door Accessibility:

 

a)     J.F. Kennedy School - Replace ramp - No action

b)     Aquidneck School - 5 x 5 landing at east entrance - No action

 

 

18)      High School Greenhouse

 

a)      The Greenhouse is complete and has been inspected by building official and Fire Department.  Final cost was approximately $165,000.00

b)      All structures, except for the greenhouse, have been taken down.  We will pick back up on this in spring.

 

19)      Security

 

a.       Middletown High School - Card system is up and running

 

20)         Fire Upgrade

 

a.       Oliphant School - New fire panel - Complete

b.      Middletown High School - New fire panel - Complete

c.       J.H. Gaudet School - New fire panel - Complete