BUILDINGS AND GROUNDS
NOVEMBER REPORT SUBMITTED BY EDWARD COLLINS
District Wide Project List 2005-2006
1)
Flooring: On-going
replacement program
i)
Gaudet: Lower level corridor scheduled for Christmas
and February vacation/CIP money
ii)
2)
Whiteboards: On-going
in-house chalkboard replacement
i) MHS -
100% done
ii) Gaudet
- 100% done
iii)
Elementary- 70%
done
3)
Bulletin
Boards: On-going in-house replacement program
i)
MHS - 80% done
ii)
Gaudet - 80% done
iii)
Elementary - 90%
done
4)
Exterior
Painting and Lead encapsulation: In-house program
i)
MHS - 75% done
ii)
Gaudet - 50% done
5) Interior
Painting: On-going in-house program
i)
MHS - On hold
until winter
ii)
Gaudet - Done
iii)
Elementary - On
hold until winter
6)
Bookcases: ongoing in house program
i) MHS -
95% done
ii) Gaudet
-95% done
iii) JFK -
75% done
iv) Aquidneck/Forest - No action
7)
Paving, safety
and drainage program: 10 year management plan written by Louis
Berger Group.
i) Gaudet - Entrance and front parking
lot scheduled for spring/CIP money
ii) Forest Ave- Front parking and drive
scheduled for spring/CIP money
8)
Interior
i) High School - Complete
ii) Rest of District- On-going/20% done
9) Interior Door hardware: On-going program to make all door hardware
i) High School- Complete
10) Acoustics: The following areas have been designated for
some type of acoustical treatment
i)
Forrest gym - No
action
ii)
JFK cafeteria -
No action
iii)
Gaudet cafeteria
- No action
11) Roof update: Bond
i)
Gaudet - Add four
roof drains - Complete
ii)
Aquidneck –
Repaired leak in Annex - Complete
12)
Restrooms: District wide
a)
Replace Bradley
sinks
i) Gaudet - Complete
ii) High School - Complete
b)
Replace gravity
feed urinals - Complete
c) Increase size of stalls to comply with ADA-in
progress
i) MHS - Complete
ii) Gaudet - Complete
d)
Lower mirrors-in progress
i) MHS Complete/will add regular mirrors
ii) Gaudet Complete
13)
Add grab bars -In
progress
i)
MHS Complete
ii)
Gaudet Complete
14)
Other
i) Forrest
Ave - remove large box covering old toilet area and repair floor- No action
ii)
15)
Other plumbing
improvements:
a)
Add two sinks in
annex at JFK- Complete
16)
Handrails: District wide
- No action
17)
Exterior door
accessibility:
i)
JFK replace ramp
- No action
ii)
Aquidneck: 5 x 5 landing at east entrance - No action
18) High
School Greenhouse
i) The Greenhouse is complete and has
been inspected by building official
and Fire
Department. Final cost was approx. $165,000.00
ii) Old greenhouse and barn have been taken
down
THIS MONTH WE WILL BE DOING RADON TESTING IN ALL
SCHOOLS AND ALSO DOING THE ANNUAL INDOOR AIR QUALITY TEST IN ALL SCHOOLS