OCTOBER  REPORT SUBMITTED BY EDWRAD COLLINS

 

 

BUILDINGS AND GROUNDS

 

 

DISTRICT WIDE PROJECT LIST

 

 

 

1)      FLOORING: ongoing replacement program

 

 

i)                    JFK- COMPLETE

ii)                  High School-gym foyer area/waiting for materials

iii)                High School-asbestos removal/lined up for school vacations

iv)                Gaudet classrooms-asbestos removal/lined up for school vacation

 

 

2)      EXTERIOR PAINTING/LEAD ENCAPSULATION

 

               

i)                    High School- 80% done

ii)                  Gaudet- 80% done           

iii)                JFK- 25% done

 

 

3)      INTERIOR PAINTING

 

 

i)                    Forest Ave- will start in November

 

 

4)      BLINDS

 

i)                    JFK-90% DONE

ii)                  Gaudet -COMPLETE

 

 

 

 

5)   PAVING

 

i)                     Gaudet- finish curbing and sidewalks

ii)                  Aquidneck- front entrance /spring

iii)                High School- back walk way/spring

 

 

6)      EXTERIOR DOOR ACCESSIBILITY

 

i)                     JFK- replace ramp/in progress

ii)                   JFK-repair thresholds at all doors/in progress

 

   

 

 

      7)   INTERIOR DOOR HARDWARE

               

 

                     i)      Gaudet-in progress/custodial and office doors

         

 

8)      ROOF

 

i)                     Aquidneck- in spring

ii)                  High School-section of roof over 248/in progress

 

 

        9)    FIRE UPGRADE

 

 

i)                    High School- addition of pull station/heat-smoke and strobes 95%  

Done

 

10)   GENERATORS

iii)                High School- in progress

iv)                Gaudet-in progress

v)                  Oliphant- in progress

      

 

11)     FIELDS- slicing/aerating/seeding/fertilize/lime

                      All work being done collectively with public works

 

a.       High School- front practice area-in progress

b.      Gaudet-baseball/football/practice area-in progress