SEPTEMBER REPORT SUBMITTED BY EDWRAD COLLINS

 

 

BUILDINGS AND GROUNDS

 

 

DISTRICT WIDE PROJECT LIST

 

 

 

 

 

1)      FLOORING: ongoing replacement program

 

 

i)                    JFK- area rugs in classrooms in progress

ii)                  High School-gym foyer area/waiting for materials

iii)                High School-asbestos removal/lined up for school vacations

iv)                Gaudet classrooms-asbestos removal/lined up for school vacation

 

 

 

2)      EXTERIOR PAINTING/LEAD ENCAPSULATION ( ALL PAINTING ON HOLD)

 

               

i)                    High School- 80% done

ii)                  Gaudet- 80% done           

iii)                JFK- 25% done

 

 

3)      INTERIOR PAINTING ( ALL PAINTING ON HOLD)

 

 

i)                    Forest Ave- will start in November

 

 

 

4)      BLINDS

 

i)                    JFK-in progress

ii)                  Gaudet -complete

 

 

 

 

 

 

 

 

 

5)   PAVING

 

i)                     Gaudet- finish curbing and sidewalks

ii)                  Aquidneck- front entrance /spring

 

 

6)      EXTERIOR DOOR ACCESSIBILITY

 

i)                     JFK- replace ramp/in progress

ii)                   JFK-repair thresholds-complete

 

  

 

 

      7)   INTERIOR DOOR HARDWARE

               

 

                     i)      Gaudet-in progress/custodial and office doors

         

 

8)      ROOF

 

i)                     Aquidneck- in spring

 

 

        9)    FIRE UPGRADE

 

 

i)                    High School- addition of pull station/heat-smoke and strobes 95%  

Done